Calculate backwards

K

Kay

Hi
I have a set end date. From this end date I want to calculate
backwards to see when I need what.
I have all durations and work estimated so there must be a way that I
can calculate backwards.
But I don't find it
Or is it simply saying:
Finish as late as possible for each task?

Thanks
Kay
 
J

Jan De Messemaeker

Hi Trevor and all,


Project is much richer than that.
No need to set the calculate from finish option.
Wanna know the latest dates? Simply show them (Late Start, Late Finish) -
Insert Columns does the trick
And moreover Project gently offers you the difference betwen late and early-
Total Slack
No need to calculate from finish indeed - CPM always calculates BOTH dates.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top