R
Rob S.
My question for you is as follows: How can I calculate the % complete for
specific summary tasks? The following background may be helpful and
(hopefully) should clarify my question.
We are using MS Project 2007 in a very elementary way, basically just as a
project scheduling tool. For example, we are not using any of the advanced
features like baselines and resource leveling. In fact, some of our tasks do
not even have resources assigned to them - they are entered as fixed costs to
approximate the planned activities.
My problem centers on another caveat of this project. A few of the tasks
will be completed by our customer, however, these tasks are integral to the
overall project schedule. Therefore, we need to include them, along with
their full durations, to monitor our schedule. However, by including the full
durations of the customer's tasks, our % complete is skewed. We need the %
complete for our portion of the project, not the entire project.
Currently we must zero out the duration on the customer's tasks temporarily
in order to calculate the % complete for our portion of the project. I'm
hoping that the community can suggest a better solution.
Thank you!
Rob S.
specific summary tasks? The following background may be helpful and
(hopefully) should clarify my question.
We are using MS Project 2007 in a very elementary way, basically just as a
project scheduling tool. For example, we are not using any of the advanced
features like baselines and resource leveling. In fact, some of our tasks do
not even have resources assigned to them - they are entered as fixed costs to
approximate the planned activities.
My problem centers on another caveat of this project. A few of the tasks
will be completed by our customer, however, these tasks are integral to the
overall project schedule. Therefore, we need to include them, along with
their full durations, to monitor our schedule. However, by including the full
durations of the customer's tasks, our % complete is skewed. We need the %
complete for our portion of the project, not the entire project.
Currently we must zero out the duration on the customer's tasks temporarily
in order to calculate the % complete for our portion of the project. I'm
hoping that the community can suggest a better solution.
Thank you!
Rob S.