K
Keith
I need help calculating Dates in Project where milestone events will be
repeated throughout the project.
As an example: I have a project plan to clean up all garages on my
street. The milestone event is the Street Address *3504 *and each task
will occur at a set number of days for each Street Address.
3504 is set to begin on *6/1/07*.
- Order Paint 3 week lead time *(5/11/07) = 6/1/07 - 21 days*
- Order Brooms 2 week lead time *(5/18/07) = 6/1/07 - 14 days*
- Order Mops 1 week lead time *(5/25/07) = 6/1/07 - 7 days*
And I want everything to *arrive at 3504 on 6/1/07*.
HOW DO I ENTER A FORMULA TO CALCULATE THE 5/11/07, 5/18/07 AND 5/25/07
DATES?[/B] THE PLAN CANNOT BE BUILT USING PREDECESSORS AS MANY EVENTS
WILL BE RUNNING CONCURRENT WITH THE START DATE BEING THE ONLY
PREDECESSOR.
NOW FOR THE TRICKY PART. . . THE PLAN SHOULD NOW BE UPDATED BY COPYING
ALL OF THE ROWS FROM 3504 TO THE NEW ADDRESSES 3507 WITH A START DATE
OF 7/1/07 AND EVENTUALLY 8217 WITH A START DATE OF 2/27/09. THE
ARRIVAL DATES SHOULD AUTO POPULATE FOR STREET ADDRESSES 3507 AND 8217
BY ONLY CHANGING THE START DATE.
Any help is greatly appreciated,
Keith
repeated throughout the project.
As an example: I have a project plan to clean up all garages on my
street. The milestone event is the Street Address *3504 *and each task
will occur at a set number of days for each Street Address.
3504 is set to begin on *6/1/07*.
- Order Paint 3 week lead time *(5/11/07) = 6/1/07 - 21 days*
- Order Brooms 2 week lead time *(5/18/07) = 6/1/07 - 14 days*
- Order Mops 1 week lead time *(5/25/07) = 6/1/07 - 7 days*
And I want everything to *arrive at 3504 on 6/1/07*.
HOW DO I ENTER A FORMULA TO CALCULATE THE 5/11/07, 5/18/07 AND 5/25/07
DATES?[/B] THE PLAN CANNOT BE BUILT USING PREDECESSORS AS MANY EVENTS
WILL BE RUNNING CONCURRENT WITH THE START DATE BEING THE ONLY
PREDECESSOR.
NOW FOR THE TRICKY PART. . . THE PLAN SHOULD NOW BE UPDATED BY COPYING
ALL OF THE ROWS FROM 3504 TO THE NEW ADDRESSES 3507 WITH A START DATE
OF 7/1/07 AND EVENTUALLY 8217 WITH A START DATE OF 2/27/09. THE
ARRIVAL DATES SHOULD AUTO POPULATE FOR STREET ADDRESSES 3507 AND 8217
BY ONLY CHANGING THE START DATE.
Any help is greatly appreciated,
Keith