M
martijn.damen
Hi all,
I'm trying to pimp our ms project plan a bit.
Currently we have a project plan which is hour based, so in the
columns work, actual work and remaining work we have values in hours.
Unfortunately I have to report these as days, where we calculate each
working day with 9 hours. So I want to add a column which
automatically takes the value of the column 'actual work' and puts it
times 9 in a customer field column.
I have done the following:
add custom field duration1
customized the field duration1 with the formula "[Actual Work]/9"
But somehow the numbers don't make sense..
Who can help me out here. Tnx, Martijn
I'm trying to pimp our ms project plan a bit.
Currently we have a project plan which is hour based, so in the
columns work, actual work and remaining work we have values in hours.
Unfortunately I have to report these as days, where we calculate each
working day with 9 hours. So I want to add a column which
automatically takes the value of the column 'actual work' and puts it
times 9 in a customer field column.
I have done the following:
add custom field duration1
customized the field duration1 with the formula "[Actual Work]/9"
But somehow the numbers don't make sense..
Who can help me out here. Tnx, Martijn