D
Darren_S15
I am generating a report from MS Project 2007 in Excel showing each
task the number of days worked on it.
Each task only has one resource associated with it, although this may
have no relevance.
What I am trying to do is calculate the total number of days each task
is worked on per month.
So in Excel I would have for example October2009, November2009,
December2009 etc in the columns.
Then on the rows below a list of how many days this task has been
worked on this month.
I have searched the web and books and cannot find any easy way to do
this without writing my own modules.
Does anyone know of a solution to this?
Thanks,
Darren
task the number of days worked on it.
Each task only has one resource associated with it, although this may
have no relevance.
What I am trying to do is calculate the total number of days each task
is worked on per month.
So in Excel I would have for example October2009, November2009,
December2009 etc in the columns.
Then on the rows below a list of how many days this task has been
worked on this month.
I have searched the web and books and cannot find any easy way to do
this without writing my own modules.
Does anyone know of a solution to this?
Thanks,
Darren