S
Scott
Greetings
I have some machinery which I need to keep track of and thought project
might be the ticket. Heres the problem
The machines have a finite life span and the life is dependant on the total
electrical power they use (Kinda like a light bulb), once they get close to
the the expected power usage we like to take them out of service before they
fail. We have many different machines with different lifes. I also know the
demand on each machine per unit time say per day.
So from this information I can determine when the machine will fail and
schedule replacement and order spare machines
I would like to make a simple MS Project document to keep track of all the
machines and the spare replacement machines. It will help us keep history as
well as perdict when we need to order spares.
So the question. I would like to be able to calculate the duration in
project from two other custom fiields. For example
Duration=Expected Life/Demand
Can project calculate task duration from custom field.
Am I barking up the wrong tree
Thanks
Scott
I have some machinery which I need to keep track of and thought project
might be the ticket. Heres the problem
The machines have a finite life span and the life is dependant on the total
electrical power they use (Kinda like a light bulb), once they get close to
the the expected power usage we like to take them out of service before they
fail. We have many different machines with different lifes. I also know the
demand on each machine per unit time say per day.
So from this information I can determine when the machine will fail and
schedule replacement and order spare machines
I would like to make a simple MS Project document to keep track of all the
machines and the spare replacement machines. It will help us keep history as
well as perdict when we need to order spares.
So the question. I would like to be able to calculate the duration in
project from two other custom fiields. For example
Duration=Expected Life/Demand
Can project calculate task duration from custom field.
Am I barking up the wrong tree
Thanks
Scott