Hi,
I have a project which is broken into various tasks. One of the tasks,
let's call it documentation, has subtasks which need to occur on specific
dates. I need to identify how many days of work it will take. When I enter
all the subtasks, Project is counting the days between the start of the first
subtask and finish of the last subtask. It gives me a total of 17 days, when
there is only 13 days of work.
It only seems to be this task/subgroup - I have another one that is subtasks
on different days and it's calculating it fine! Just can get this one to do
it - what am I doing wrong?
Ta!
Sian
I have a project which is broken into various tasks. One of the tasks,
let's call it documentation, has subtasks which need to occur on specific
dates. I need to identify how many days of work it will take. When I enter
all the subtasks, Project is counting the days between the start of the first
subtask and finish of the last subtask. It gives me a total of 17 days, when
there is only 13 days of work.
It only seems to be this task/subgroup - I have another one that is subtasks
on different days and it's calculating it fine! Just can get this one to do
it - what am I doing wrong?
Ta!
Sian