S
scubaal
Using Project 2003 Pro + Server.
Is is possible to create an Enterprise Field that is a formula that
takes its value from the Actual Finish date of a task in the project.
Example:
We *always* have a task called 'Request Brief', which is completed
when the project owner has requested the breif.
I would like a Enterprise Field that gets the Actual finish date of
'Request Brief'. Is that possible?
I could then have a 2nd Enterprise field that would be a duration -
that is the no of days between 'request brief' and now.
I just cant work out whether its possible to get a value from a named
task?
Any ideas?
Thanks
Al
Is is possible to create an Enterprise Field that is a formula that
takes its value from the Actual Finish date of a task in the project.
Example:
We *always* have a task called 'Request Brief', which is completed
when the project owner has requested the breif.
I would like a Enterprise Field that gets the Actual finish date of
'Request Brief'. Is that possible?
I could then have a 2nd Enterprise field that would be a duration -
that is the no of days between 'request brief' and now.
I just cant work out whether its possible to get a value from a named
task?
Any ideas?
Thanks
Al