Calculate Net Work Days for 4 day weeks

D

Darin

The networkday function calculates days based on a 5 day work week. I have
staff who work 4 day weeks and would like to calculate net work days based on
the 4 day week.

Any ideas of how to do this.
 
M

Mike H

Hi,

Which is the weekday they don't work? if it's a Friday try this

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&B1)),2)<5),--(ISNA(MATCH(ROW(INDIRECT(A1&":"&B1)),C1:C8,0))))

Where a1 and B1 are the start end days and C1 - c8 are any holidays you wabt
to exclude.

Mike
 
D

Darin

Hi,
Friday is the day they don't work, but when I try the coding you suggested I
am not getting a correct result. Admitidly I have not familiar with some of
the functions you suggested.
I specified a begin date of 7/5/2009 and an end date of 7/18/2009 and no
holiday, and expected the result to be 8, but am getting 22.

This is the formula I tried ... did I get something wrong?
=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&B1)),2)<5)--(ISNA(MATCH(ROW(INDIRECT(A1&":"&B1)),C1,0))))

Thanks
Darin
 
B

Bernd P

Hello,

A solution without holidays:
=A2-A1+1-INT((A2-MOD(A2-1,7)-A1+7)/7)-INT((A2-MOD(A2-6,7)-A1+7)/7)-INT
((A2-MOD(A2-7,7)-A1+7)/7)

A1: Start Date
A2: End Date

Regards,
Bernd
 