froggygremblin
I want to calculate the number of days worked on a project in a rolling 4
month calendar. Working Days are Mon-Thu. My sheet looks like this:
Jobname TotalDays StartDate EndDate DaysMo1 DaysMo2 DaysMo3 DaysMo4
Foo 3 3-22-10 3-25-10 3 0
0 0
Goo 25 4-2-10 5-17-10 0 17 8
0
I have used Workday to calculate my enddate but I'm having difficulty
calculating the proper month bins to put the days in. Since the calendar
rolls forward ewach month I need to consider that a job started before Mo1 or
in Mo1 or in Mo2 or in Mo4 or it'sw beyond the planning horizon. Anyone
solved this before?
Thanks for any guidence
month calendar. Working Days are Mon-Thu. My sheet looks like this:
Jobname TotalDays StartDate EndDate DaysMo1 DaysMo2 DaysMo3 DaysMo4
Foo 3 3-22-10 3-25-10 3 0
0 0
Goo 25 4-2-10 5-17-10 0 17 8
0
I have used Workday to calculate my enddate but I'm having difficulty
calculating the proper month bins to put the days in. Since the calendar
rolls forward ewach month I need to consider that a job started before Mo1 or
in Mo1 or in Mo2 or in Mo4 or it'sw beyond the planning horizon. Anyone
solved this before?