R
Ratnadeep
Hi, In my organisation we need to track the schedule & effort slippage on a
percentage basis.e.g if the actual duration is 20% more than planned duration
we make it red. Similarly for green & yellow.. For effort we need to track
the effort variance on a percentage basis. e.g actual effort is 20 % more
than planned effort,then we display red. How can we do that?
Currently i am following the similar steps suggested by Dale in one of the
article. If the finish variance is more 30 days we show the project as REd &
similarly for green & yellow. For effort we are tracking the work variance.
e.g if the work varaince is more than 50 h we show the task or project as
red. But we need to change these methods as these are not giving the desired
results always. I tried the following:
1)For schedule slippage: Finish variance/baseline finish in the formula
tab.then in the graphical indicator i made it Red if it is greater or equal
to .02.& similarly for others.
2)For effort slippage:work variance/work in the formula tab.Then in the
graphical indicator i made it red if the variance is greater or equal to .02
i.e 20%. Similarly for others.
3)I selected individual projects & press F9 to update the changes.
But it is not working. It is rellay messing up things. Also the graphical
indicator field is showing the value in days (20d) & not in percentage. We
are using PS 2003. Can you please help me out ?
Thanks,Ratnadeep,PMP
percentage basis.e.g if the actual duration is 20% more than planned duration
we make it red. Similarly for green & yellow.. For effort we need to track
the effort variance on a percentage basis. e.g actual effort is 20 % more
than planned effort,then we display red. How can we do that?
Currently i am following the similar steps suggested by Dale in one of the
article. If the finish variance is more 30 days we show the project as REd &
similarly for green & yellow. For effort we are tracking the work variance.
e.g if the work varaince is more than 50 h we show the task or project as
red. But we need to change these methods as these are not giving the desired
results always. I tried the following:
1)For schedule slippage: Finish variance/baseline finish in the formula
tab.then in the graphical indicator i made it Red if it is greater or equal
to .02.& similarly for others.
2)For effort slippage:work variance/work in the formula tab.Then in the
graphical indicator i made it red if the variance is greater or equal to .02
i.e 20%. Similarly for others.
3)I selected individual projects & press F9 to update the changes.
But it is not working. It is rellay messing up things. Also the graphical
indicator field is showing the value in days (20d) & not in percentage. We
are using PS 2003. Can you please help me out ?
Thanks,Ratnadeep,PMP