calculate total hours based on dates

C

cpliu

I have the following columns:
Date Start,Date End,Project,Hour
I'd like to input the project name in multiple rows, enter a range to cover in date start and date end, then it will calculate the total hours for each project used in that period of time.
I had the following formula working based on the range of rows to calculate, but what change do I need in order to add up based on the dates?

=SUMPRODUCT(($B$1768:$B$1793=C2)*($E$1768:$E$1793))
B column is the projects entered in the column
E is the time spent on project in B column
C2 is the project name entered to match.

Thanks,

cpliu
 
C

cpliu

What's wrong with the following, I got 0 for the total of each row.

=SUMPRODUCT(--(Data!$B$3:$B$7000>=A3),--(Data!$B$3:$B$7000<=B3),--(Data!$B$3:$B$7000=C3),(Data!$E$3:$E$7000))

B column: project names
A3 = start date
B3 = end date
E column = time spent on each project entry
 
A

Alex Plantema

cpliu schreef in
What's wrong with the following, I got 0 for the total of each row.

=SUMPRODUCT(--(Data!$B$3:$B$7000>=A3),--(Data!$B$3:$B$7000<=B3),--(Data!$B$3:$B$7000=C3),(Data!$E$3:$E$7000))

B column: project names
A3 = start date
B3 = end date
E column = time spent on each project entry

You compare dates with project names.
 
C

cpliu

You compare dates with project names.
Thank you alex. I thought what it means was to find all the column B data between dates in A3 and B3, put the total hours for the project name in B3.

Use the example below:
1. data in Data worksheet.
date, project name, hours spent
--------------------------------
7/9/2012,project 1,1.5
7/9/2012,project 2,1
7/9/2012,project 3,4
7/10/2012,project 4,1.5
7/10/2012,project 2,3
7/10/2012,project 3,2
7/11/2012,project 1,4.5
7/12/2012,project 2,3
7/12/2012,project 3,2
7/12/2012,project 4,2
7/13/2012,project 2,5.5

I'd like to find out total hours worked on each project for the past week. use the example above, I'd like to get the numbers in the hours column like the one below:
date start,date end,project,hours
----------------------------------
7/9/2012,7/13/2012,project 1,6
7/9/2012,7/13/2012,project 2,12.5
7/9/2012,7/13/2012,project 3,8
7/9/2012,7/13/2012,project 4,3.5

Please advise the right formula to get these numbers.

Thanks,
 
A

Alex Plantema

cpliu schreef in
Use the example below:
1. data in Data worksheet.
date, project name, hours spent
--------------------------------
7/9/2012,project 1,1.5
7/9/2012,project 2,1
7/9/2012,project 3,4
7/10/2012,project 4,1.5
7/10/2012,project 2,3
7/10/2012,project 3,2
7/11/2012,project 1,4.5
7/12/2012,project 2,3
7/12/2012,project 3,2
7/12/2012,project 4,2
7/13/2012,project 2,5.5

I'd like to find out total hours worked on each project for the past
week. use the example above, I'd like to get the numbers in the hours
column like the one below: date start,date end,project,hours
----------------------------------
7/9/2012,7/13/2012,project 1,6
7/9/2012,7/13/2012,project 2,12.5
7/9/2012,7/13/2012,project 3,8
7/9/2012,7/13/2012,project 4,3.5

It's probably easier to use a pivot table, though the layout of the result may be a bit different.
Select the table, start the pivot table wizard,
drag the date to the rows field, the projects to the columns field,
and the hours to the data field.
 
C

cpliu

Thank you for your help and suggestion on pivot table (learning more on it now). You are correct that I compare the name to the date, once changed, it's working.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top