A
Ahmed Ghaith
Dear All,
I used project server 2007 sp2 with SQL server 2005
Assume one resource has enter his\her actual work for 200 hours per one
month on several projects, but the default value for actual work for project
server is calculated by (8 hours * 22 actual days per month) = 176 hours per
month and is 100% per month work complete.
It means that I have 24 hours (sub. between 200 (enter actual work) and 176
(default value))
This problem increased the cost for that resource on projects, how can I
decrease or convert or calculate this value (200) to default average value
(176).
Regarding that I don’t use remaining work.
These two cases how to explain my issue:
Project A
Project B
Case 1: I entered 12 hours actual works on Monday for Project A == then it’s
calculated by 8 hours on Monday and 4 hours on Tuesday (increased project
costing).
Case 2: I entered 6 hours for project A and 6 hours for Project B on Monday
== it’s Ok for projects costing.
Regards,
Ahmed Ghaith
I used project server 2007 sp2 with SQL server 2005
Assume one resource has enter his\her actual work for 200 hours per one
month on several projects, but the default value for actual work for project
server is calculated by (8 hours * 22 actual days per month) = 176 hours per
month and is 100% per month work complete.
It means that I have 24 hours (sub. between 200 (enter actual work) and 176
(default value))
This problem increased the cost for that resource on projects, how can I
decrease or convert or calculate this value (200) to default average value
(176).
Regarding that I don’t use remaining work.
These two cases how to explain my issue:
Project A
Project B
Case 1: I entered 12 hours actual works on Monday for Project A == then it’s
calculated by 8 hours on Monday and 4 hours on Tuesday (increased project
costing).
Case 2: I entered 6 hours for project A and 6 hours for Project B on Monday
== it’s Ok for projects costing.
Regards,
Ahmed Ghaith