Calculated Dates not correct

C

csbrown

I have a resources that can work 50% on a particular project. Th
resource dialog shows that the resource is available 50%

I have a task that I have estimated to take 2 days.
I assign this resource to the task.
The completed date still shows 2 days from the start date. Since thi
resource can only work 50% of the time, shouldn't the complete date no
be 4 days from the start date?

Thanks
 
M

Mike Glen

Hi csbrown ,

Welcome to this Microsoft Project newsgroup :)

Project will assume you know what you're doing when you first assign a
resource. If the resource has only 50% availability, Project assumes you
want him to work at that level for the 2 days of the Duration. If you had
assigned him for 2 days at 100%, the Duration would still be 2 days,
However, if you subsequently reduce the assignment to 50%, then by default,
the Duration will increase to 4 days.

For more detailed guidance you might like to have a look at my series on
Microsoft Project in the TechTrax ezine, particularly #11 on task types, at
this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 