I have a resources that can work 50% on a particular project. Th
resource dialog shows that the resource is available 50%
I have a task that I have estimated to take 2 days.
I assign this resource to the task.
The completed date still shows 2 days from the start date. Since thi
resource can only work 50% of the time, shouldn't the complete date no
be 4 days from the start date?
Thanks