G
Greg L
I'm trying to setup a formula that automatically counts
down in gradations from my deadline date and triggers the
stoplights, i.e 30 days from deadline would be yellow;
beyond 30 days-green; and Red on the deadline and
beyond.
Scenario groundrules: Percent complete =0%,Work
accomplished = 0, duration = no change and no other manual
data entries allowed.
Scenario assumpution: Task(s)/Program has slipped thur
the cracks and no work has begun. As tasks approach their
deadline(s) the stoplights are automatically triggered.
Thanks in Advance!
down in gradations from my deadline date and triggers the
stoplights, i.e 30 days from deadline would be yellow;
beyond 30 days-green; and Red on the deadline and
beyond.
Scenario groundrules: Percent complete =0%,Work
accomplished = 0, duration = no change and no other manual
data entries allowed.
Scenario assumpution: Task(s)/Program has slipped thur
the cracks and no work has begun. As tasks approach their
deadline(s) the stoplights are automatically triggered.
Thanks in Advance!