C
clifton
In the planning phase of a project, duration for a task is a function of the
number of units that need to flow through that task and the capacity for that
task. I want the duration field to be calculated from a quantity and
capacity field. My planning buckets are in weeks.
I added two number columns for quanitity and capacity. I use a formula in
the duration column. The only time the duration is correct is when the
duration in the schedule tab is to minutes. This seems to be the default and
I can't seem to override the results. Changing duration and work units to
weeks doesn't yield the correct answer. Any suggestions?
number of units that need to flow through that task and the capacity for that
task. I want the duration field to be calculated from a quantity and
capacity field. My planning buckets are in weeks.
I added two number columns for quanitity and capacity. I use a formula in
the duration column. The only time the duration is correct is when the
duration in the schedule tab is to minutes. This seems to be the default and
I can't seem to override the results. Changing duration and work units to
weeks doesn't yield the correct answer. Any suggestions?