Calculating a per calendar week of usage cost for resources

P

poordan

I need to calculate a per calendar week of usage cost for resource.

Assume Res#1 is assigned to a single Task#1. Task#1's duration is 8
days. The 8 days are split over two calendar weeks on a normal work
schedule. Therefore, Res#1 will be on site for 2 calendar weeks,
although week 2 will be for less than 5 days.

I need to calculate a per week on site cost (travel costs) for the
resource.

Ideas? Thanks, Dan
 
M

Mike Glen

Hi Dan,

This sounds lie a job for vba. Try posting on the developer newsgroup.
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 