C
Cole
I'm using a computer with MS Project Professional 2003 - Service Pack
3.
I have a master file that is incorporating 30 project files. The
master file has enabled the feature "Actual Costs are alway calculated
by Microsoft Office Project". All sub files have enabled this feature
as well except for one file. The 29 files who have enabled "Actual
Costs are alway calculated by Microsoft Office Project" share one
resource pool in the master file.
The one lone file that hasn't enabled "Actual Costs are alway
calculated by Microsoft Office Project" is not resource loaded and is
using Fixed Costs to calculate Actual Cost.
When I break the link from the fixed cost project file within the
master file, it automatically defaults to "Actual Costs are alway
calculated by Microsoft Office Project", which should be expected.
I have an activity that completed on 9/30 and the status date of the
file is 10/31. When I break the link within the master file the fixed
cost project file defaults to "Actual Costs are alway calculated by
Microsoft Office Project" and the fixed cost increases the amount
entered. Keep in mind this file has no resources.
What could be causing this?
Cole
3.
I have a master file that is incorporating 30 project files. The
master file has enabled the feature "Actual Costs are alway calculated
by Microsoft Office Project". All sub files have enabled this feature
as well except for one file. The 29 files who have enabled "Actual
Costs are alway calculated by Microsoft Office Project" share one
resource pool in the master file.
The one lone file that hasn't enabled "Actual Costs are alway
calculated by Microsoft Office Project" is not resource loaded and is
using Fixed Costs to calculate Actual Cost.
When I break the link from the fixed cost project file within the
master file, it automatically defaults to "Actual Costs are alway
calculated by Microsoft Office Project", which should be expected.
I have an activity that completed on 9/30 and the status date of the
file is 10/31. When I break the link within the master file the fixed
cost project file defaults to "Actual Costs are alway calculated by
Microsoft Office Project" and the fixed cost increases the amount
entered. Keep in mind this file has no resources.
What could be causing this?
Cole