Hi Deluth,
Welcome to this Microsoft Project newsgroup
Reading between you lines, I get the impression that you are typing in the
dates for your tasks. Doing this will create constraints that are causing
the problems you see. Try View/Table: Entry/More Tables.../ and select
Constraint Dates. Reset all the Constraints to As Soon As Possible to
remove the Constraints (Change the top one and Fill Down). Project is
designed to work by scheduling from the Project Start Date (set in
Project/Project Information). So, for each task, enter the Duration and
then the Precedence logic links. Project will then calculate the Start and
Finish Dates for you.
FAQs, companion products and other useful Project information can be seen at
this web address: <
http://www.mvps.org/project/>
Hope this helps - please let us know how you get on

)
Mike Glen
MS Project MVP
Deluth said:
I have a series of tasks that are date dependent. I would like to set
dependencies so that if I set the start date of the first task, it would
calculate everything in the middle and then the end date to the last task.
However, if I set the end date to the last task, I would also like the same
calculation to occur for all the middle tasks back to the first task. I
tried doing this, but could not because the middle tasks can not be both a
predecessor to the same task that it depends on. Is there anyway I can
accomplish this? Thanks for the help.