Calculating cost in PERT analysis

I

Ian Coletti

Hi all!

I'm trying to calculate the optimistic and pessimistic costs along with
duration. It looks like Project only provides duration and no work
(therefore cost) estimates. Any idea on how to do this?

Thanks!

Ian Coletti
 
J

JackD

I haven't done this, but if you use fixed units then I would think that you
would get the right number.
You will have to copy the pessimistic durations into the duration column to
achieve this effect however. Make sure you have the original duration saved
off somewhere.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top