C
Chris
I have approximately 200 rows of tasks in column C with the estimated
number of days each task should take to complete (0, .25, 3, etc) in
column K. I am trying to use a formula so I enter a start date for
the first task, Excel adds the number of days for that task and gives
me the finish date for the first task ( but excludes holidays and
weekends). The formula will then be repeated for each row to give me
the end date for the task in that row. Any ideas on how to accomplish
this? I am basically trying to create a Project schedule in Excel.
number of days each task should take to complete (0, .25, 3, etc) in
column K. I am trying to use a formula so I enter a start date for
the first task, Excel adds the number of days for that task and gives
me the finish date for the first task ( but excludes holidays and
weekends). The formula will then be repeated for each row to give me
the end date for the task in that row. Any ideas on how to accomplish
this? I am basically trying to create a Project schedule in Excel.