Glenn
Hi all,
I am incorporating a cost estimate that I have successfully imported to
Project from Excel. I have one field named "Daily Output" and another named
"Quantity". Both are Number fields as Number1 and Number2 respectively. If
I have a Daily Output of 100 and my Quantity is 1000, then I should provide a
Duration of 10 days, if the task is not split. Can I have Project take the
values in these two fields and calculate the duration?