J
John
I am having trouble figuring out how to calculate an end date, give the fact
that a work crew can work 4, 5, 6, or 7 days a week and the activity will
take X working days. Here's a simple setup:
A1 - Start Date (Provided by Crew)
A2 - Work Schedule (4,5,6 or 7 days a week)
A3 - Duration of Activity (in working days - 10 for example)
A4 - End Date (what I want to calculate)
All workdays start on Monday. So if an activity sarts on 9/28/09 and is 10
days long and the crew is working 4/10's (4 days a week, 10 hours a day),
then the calculated end date should be 10/13/09 because 10/02 - 10/04 is
non-work and 10/09 to 10/11 is also non-work.
Any help would be great!
that a work crew can work 4, 5, 6, or 7 days a week and the activity will
take X working days. Here's a simple setup:
A1 - Start Date (Provided by Crew)
A2 - Work Schedule (4,5,6 or 7 days a week)
A3 - Duration of Activity (in working days - 10 for example)
A4 - End Date (what I want to calculate)
All workdays start on Monday. So if an activity sarts on 9/28/09 and is 10
days long and the crew is working 4/10's (4 days a week, 10 hours a day),
then the calculated end date should be 10/13/09 because 10/02 - 10/04 is
non-work and 10/09 to 10/11 is also non-work.
Any help would be great!