M
Martin
I would appreciate some help with a project. I'm using Project 2003.
Some of the tasks in the WBS need to be tracked with a 5 day per week /
8 hours a day calendar. Other tasks need to be tracked with a 24 hr per
day / 7 day a week calendar.
I set up the calendar to be 5 days per week / 8 hours per day. This
works best for 70% of the tasks. For example if the tasks will take 10
day of work to complete, I enter 10d in the duration and the start to
finish time is a total of 14 days; which includes 4 week end days when
no work will be accomplished. This is correct.
However, 30% of the tasks are the kind that will be accomplished on a
24 hour per day / 7 day a week schedule. For example some of these
tasks will take 72 hours (3 days at 24 hrs per day) for the 24 / 7 shop
floor to fabricate. If I enter 3 days the start to finish time will add
in weekend time, which is not correct. If I enter 72 hours, the start
to finish time is 9 days plus weekends.
There are probably several ways to resolve this problem in Project.
Many projects must have this kind of situation. I'd appreciate some
recommendations about the best way to deal with this situation.
Thanks,
Martin
Some of the tasks in the WBS need to be tracked with a 5 day per week /
8 hours a day calendar. Other tasks need to be tracked with a 24 hr per
day / 7 day a week calendar.
I set up the calendar to be 5 days per week / 8 hours per day. This
works best for 70% of the tasks. For example if the tasks will take 10
day of work to complete, I enter 10d in the duration and the start to
finish time is a total of 14 days; which includes 4 week end days when
no work will be accomplished. This is correct.
However, 30% of the tasks are the kind that will be accomplished on a
24 hour per day / 7 day a week schedule. For example some of these
tasks will take 72 hours (3 days at 24 hrs per day) for the 24 / 7 shop
floor to fabricate. If I enter 3 days the start to finish time will add
in weekend time, which is not correct. If I enter 72 hours, the start
to finish time is 9 days plus weekends.
There are probably several ways to resolve this problem in Project.
Many projects must have this kind of situation. I'd appreciate some
recommendations about the best way to deal with this situation.
Thanks,
Martin