G
Glenn
I have a table setup as follows:
Task Name ------- Total Cost --- Amount Paid --- Balance Remaining
=========================================
Project Summary $170 $50 $120
Task A
Task 1a $100 $30 $70
Task 2a $50 $0 $50
Task B
Task 1b $20 $20 $0
Can anyone tell me how to set up these fields to calculate accrodingly?
Excel seems much more intuitive than Project. I have a lot of reference and
some coding background and yet the solution to this seemingly simple task
appears all too difficult via Project...
Thanks for any feedback or help on this
Task Name ------- Total Cost --- Amount Paid --- Balance Remaining
=========================================
Project Summary $170 $50 $120
Task A
Task 1a $100 $30 $70
Task 2a $50 $0 $50
Task B
Task 1b $20 $20 $0
Can anyone tell me how to set up these fields to calculate accrodingly?
Excel seems much more intuitive than Project. I have a lot of reference and
some coding background and yet the solution to this seemingly simple task
appears all too difficult via Project...
Thanks for any feedback or help on this