Calculation of Slack

T

Tracey

I have a large project which culminates to a completion of construction. In
the same project I have contractual and handover milestones which have to be
reached after the construction has been completed. These contractual
milestones determine the end date of the project, which is about 1 Year after
construction. The problem that I have is that I would like the total slack to
be calculated on the construction completion date. As it is at the moment I
have 300 days slack, but this is due to contractual milestone completion. Is
this possible? Can I create a custom claculation? The contractual Milestone
start is dependent on the construction completion, so I would like it as part
of the same project file.
Thanx
 
T

Trevor Rabey

First thing that comes to mind (not likely the best solution) is to keep the
construction part as a project on its own and then insert it into the
project which as the late milestones init.
 
J

Jan De Messemaeker

Hi,

Don't link the "real" tasks to the finishing milestones and in tools,
options, Calculation, check on "Calculate Multiple Critical paths"
HTH
 