T
Tracey
I have a large project which culminates to a completion of construction. In
the same project I have contractual and handover milestones which have to be
reached after the construction has been completed. These contractual
milestones determine the end date of the project, which is about 1 Year after
construction. The problem that I have is that I would like the total slack to
be calculated on the construction completion date. As it is at the moment I
have 300 days slack, but this is due to contractual milestone completion. Is
this possible? Can I create a custom claculation? The contractual Milestone
start is dependent on the construction completion, so I would like it as part
of the same project file.
Thanx
the same project I have contractual and handover milestones which have to be
reached after the construction has been completed. These contractual
milestones determine the end date of the project, which is about 1 Year after
construction. The problem that I have is that I would like the total slack to
be calculated on the construction completion date. As it is at the moment I
have 300 days slack, but this is due to contractual milestone completion. Is
this possible? Can I create a custom claculation? The contractual Milestone
start is dependent on the construction completion, so I would like it as part
of the same project file.
Thanx