Andy B

I am trying to calculate the difference between one cell and another - both
having dates in, to establish if a service level is being achieved for
completing a task.

eg. B2 = 25/6/07 and L2 = 30/6/07 (5 days)

currently if there is no date in L2, it will say "open call" - indicating
that it has not been completed.

the calculation used currently is =IF(ISERROR(DAYS360(B2,L2,TRUE)),"Open
Call",DAYS360(B2,L2,TRUE)) however this does not show working days taken to
complete the call, which is key to the measurement.

have tried advice below, but unfortunately it still includes the weekend
days - can I
include the WEEKDAYS or NETWORKDAYS formula in this somehow? thanks
 
B

Bernie Deitrick

Andy,

=IF(L2="", "Open Call",NETWORKDAYS(B2,L2))

HTH,
Bernie