L
Louise Anderson
I read all the postings on multiple baselines (thank you for making it clear
that the interim plan idea is a bad one).
My issue is this- I have set up a view that shows Baseline Start/Finish,
Start/Finish and Baseline1 Start/Finish. I am only updating selected tasks.
When I update the Baseline1 Start date it is not updating Baseline1 Finish
date, nor are the summary tasks updating.
I am sure this is something really easy, some option I am not turning on. We
have it set to Autocalculate and I verified that it does calculate as
expected when I change a Start date. I also had it set to roll up to summary
tasks for the selected tasks.
(Using MS Project 2003 SP2)
Thanks in advance
that the interim plan idea is a bad one).
My issue is this- I have set up a view that shows Baseline Start/Finish,
Start/Finish and Baseline1 Start/Finish. I am only updating selected tasks.
When I update the Baseline1 Start date it is not updating Baseline1 Finish
date, nor are the summary tasks updating.
I am sure this is something really easy, some option I am not turning on. We
have it set to Autocalculate and I verified that it does calculate as
expected when I change a Start date. I also had it set to roll up to summary
tasks for the selected tasks.
(Using MS Project 2003 SP2)
Thanks in advance