G
Girija
Hello,
I am using 9 hrs calendar for a resource "X". I have assigned a task to this
resource and I am viewinginformation in Resource Usage in MSP 2003. I noticed
a strange behaviour. On a day the resource is showing overloading (in red
color). When I viewed in work window of the same Resource Usage page it hasnt
exceeded 9 hrs but displaying red there too! What might be the problem?
Thanks
Girija N G
I am using 9 hrs calendar for a resource "X". I have assigned a task to this
resource and I am viewinginformation in Resource Usage in MSP 2003. I noticed
a strange behaviour. On a day the resource is showing overloading (in red
color). When I viewed in work window of the same Resource Usage page it hasnt
exceeded 9 hrs but displaying red there too! What might be the problem?
Thanks
Girija N G