I
irish_archer68
Hello and thank you in advance for any insight you can shed on my
question/confusion. I have a project with a Project calendar with 6
holidays - including July 4, 2008. A task with 3 resources spans the
entire 2008 year. All 3 resources have a resource calendar based on
the out of the box standard calendar - which contains zero holidays.
When I publish this project to Project Server 2007, the duration of
this long task gets reduced by 6 days - seeming to ignore the 6
holidays included in the Project Calendar.
When I change the resource calendars to be based on the same project
calendar, the duration goes back to what I expected.
Can someone explain to me what is occuring? I would think exceptions
in the Project calendar would over ride any availbility in individaul
resource calendars. I am confused by the behavir though.
PLEASE HELP....
question/confusion. I have a project with a Project calendar with 6
holidays - including July 4, 2008. A task with 3 resources spans the
entire 2008 year. All 3 resources have a resource calendar based on
the out of the box standard calendar - which contains zero holidays.
When I publish this project to Project Server 2007, the duration of
this long task gets reduced by 6 days - seeming to ignore the 6
holidays included in the Project Calendar.
When I change the resource calendars to be based on the same project
calendar, the duration goes back to what I expected.
Can someone explain to me what is occuring? I would think exceptions
in the Project calendar would over ride any availbility in individaul
resource calendars. I am confused by the behavir though.
PLEASE HELP....