Robert
Hello,
In Propject Pro 2002, I created a task : Duration = 5 days
Calendar : Tools / Options / Calendar : 7h/day and 35h/week. Calendar :
7h/day and 35h/week
In the Global Enterprise : Tools / Options / Calendar : 7h/day and 35h/week.
Calendar : 7h/day and 35h/week
in the Resource global : Tools / Options / Calendar : 7h/day and 35h/week
Calendar : 7h/day and 35h/week
In PWA 2002 : the tasks appears with Duration = 4,38 days
Looks like 35h in a 40h/week calendar !
Where is the trick ?
Thanks for help
Robert
In Propject Pro 2002, I created a task : Duration = 5 days
Calendar : Tools / Options / Calendar : 7h/day and 35h/week. Calendar :
7h/day and 35h/week
In the Global Enterprise : Tools / Options / Calendar : 7h/day and 35h/week.
Calendar : 7h/day and 35h/week
in the Resource global : Tools / Options / Calendar : 7h/day and 35h/week
Calendar : 7h/day and 35h/week
In PWA 2002 : the tasks appears with Duration = 4,38 days
Looks like 35h in a 40h/week calendar !
Where is the trick ?
Thanks for help