M
Martin Wilkinson
I want to do something really simple and I'm not sure the best way to do it.
I've read many of the posts on the subtleties of days per month, calenders
etc.
All I want to do is say that a particular task starts approximately 12
calendar months after an event.
I want to use this to represent an approximate lead time for component
delivery. So I have a "component ordered" milestone, followed by a "component
delivered, work can start" task. I have linked the 2 tasks and added a 12
month lag.
If I use reasonable Tools/Options/Calendar settings (7.5 hrs/day,37.5
hrs/week,20 days/month), and set the first milestone to 1 Nov 05, the linked
task is driven to start on 12 Sep 06, which is about 6 weeks adrift. I don't
need it to be very accurate, but more accurate than this.
If I set days/month to 23 then they line up OK (to within a week). Is this
the best/only way? Will this cause me any other problems? What do other
people use for days/month?
I tried setting the lag to 12 emons (elapsed months) but this drove the task
29 June 06 (even worse!). Don't quite understand this.
Anyone know why the default Calendar setting of days/month is 20 which can
give such a big errors?
I suppose what I really want is to be able to tell Project to use
approximate calendar days/months for specific durations/lags, but it seems to
be too analytical to do that.
Anyone have any thoughts?
I've read many of the posts on the subtleties of days per month, calenders
etc.
All I want to do is say that a particular task starts approximately 12
calendar months after an event.
I want to use this to represent an approximate lead time for component
delivery. So I have a "component ordered" milestone, followed by a "component
delivered, work can start" task. I have linked the 2 tasks and added a 12
month lag.
If I use reasonable Tools/Options/Calendar settings (7.5 hrs/day,37.5
hrs/week,20 days/month), and set the first milestone to 1 Nov 05, the linked
task is driven to start on 12 Sep 06, which is about 6 weeks adrift. I don't
need it to be very accurate, but more accurate than this.
If I set days/month to 23 then they line up OK (to within a week). Is this
the best/only way? Will this cause me any other problems? What do other
people use for days/month?
I tried setting the lag to 12 emons (elapsed months) but this drove the task
29 June 06 (even worse!). Don't quite understand this.
Anyone know why the default Calendar setting of days/month is 20 which can
give such a big errors?
I suppose what I really want is to be able to tell Project to use
approximate calendar days/months for specific durations/lags, but it seems to
be too analytical to do that.
Anyone have any thoughts?