Calendar Goes to 1987

M

Melinda

Hi!
I have a gantt chart for my project. If I'm viewing the chart and change to
the calendar view, I'm in 1987. If I click on a task in my chart then go to
the calendar I'm in the ballpark. Is there a way to tell Project that I
don't want to go back any further than 2004?
Thanks!
Melinda
 
M

Mike Glen

Hi Melinda,

Welcome to this Microsoft Project newsgroup :)

I've never found a way round this - it must be a "feature" :)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
M

Melinda

Thanks Mike,
I love those Microsoft "features", too. Guess I'll just have to muddle
through. I'll be sure to check out the Project MVP site though!
Thanks again,
Melinda
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top