Calendar in Hours
I created a Project in Hours rather than days. I then created a new 16 hour calendar, entered the task and duration of 48 hours, which should be 3 days with a 16 hour calendar. Project calculated the finish date as 6 days later, which would be using the standard calendar. Doesn't Project like working in hours? My instructor indicated it was better to work in hours rather than days?