Calendar in days

C

Calendar in Hours

I created a Project in Hours rather than days. I then created a new 16 hour calendar, entered the task and duration of 48 hours, which should be 3 days with a 16 hour calendar. Project calculated the finish date as 6 days later, which would be using the standard calendar. Doesn't Project like working in hours? My instructor indicated it was better to work in hours rather than days?
 
J

Jan De Messemaeker

Hi,

The expression "calendar" ia ambiguous.
Please read
http://www.mvps.org/project/faqs.htm
faq 5.Default working hours

And by the way, Project works in minutes... :)
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
Calendar in Hours said:
I created a Project in Hours rather than days. I then created a new 16
hour calendar, entered the task and duration of 48 hours, which should be 3
days with a 16 hour calendar. Project calculated the finish date as 6 days
later, which would be using the standard calendar. Doesn't Project like
working in hours? My instructor indicated it was better to work in hours
rather than days?
 