M
mehunter48
We use MS Project 2003 Professional.
I am using a Resource Pool.
I set the Base Calendar for Resource A to Calendar Days, a calendar
created in the Resource Pool that uses all seven days of the week fro
7:00 to 12:00, 12:30 to 5:30, i.e., 10-hr workday.
If I enter Resource A as the Resource, 60 days as duration and
Starting date of 12/15/09 as set by a predecessor task, the Finish dat
shows 4/6/10 or 112 vs 60 calendar days.
If, using Task Information and the Adv Tab, I set Calendar: to Calenda
Days with either "Scheduling ignores resource calendars" checked o
unchecked, and the Start date is 12/15/09, the Finish date become
2/12/10, or 59 days which is correct.
I don't understand why, whenever I use the Base Calendar setting fo
Resource A in lieu of using the Calendar setting on the Adv Tab, MS
appears to use the project's base calendar, i.e., a Mon-Thr, 10 hrs/da
instead of Calendar Days. In both the Resource Pool's Resource Sheet an
the Project's Resource Sheet, the Base Calendar for Resource A shows a
Calendar Days.
Why is this happening or what am I doing wrong???
Thank you
I am using a Resource Pool.
I set the Base Calendar for Resource A to Calendar Days, a calendar
created in the Resource Pool that uses all seven days of the week fro
7:00 to 12:00, 12:30 to 5:30, i.e., 10-hr workday.
If I enter Resource A as the Resource, 60 days as duration and
Starting date of 12/15/09 as set by a predecessor task, the Finish dat
shows 4/6/10 or 112 vs 60 calendar days.
If, using Task Information and the Adv Tab, I set Calendar: to Calenda
Days with either "Scheduling ignores resource calendars" checked o
unchecked, and the Start date is 12/15/09, the Finish date become
2/12/10, or 59 days which is correct.
I don't understand why, whenever I use the Base Calendar setting fo
Resource A in lieu of using the Calendar setting on the Adv Tab, MS
appears to use the project's base calendar, i.e., a Mon-Thr, 10 hrs/da
instead of Calendar Days. In both the Resource Pool's Resource Sheet an
the Project's Resource Sheet, the Base Calendar for Resource A shows a
Calendar Days.
Why is this happening or what am I doing wrong???
Thank you