Michael Vestel
When I schedule a task to have a duration of 3 months,
starting on
Fri 10/1/04
I would like it to end on
Thu 12/31/04
but it ends on
Thu 12/23/04
What is the best way to change it so months and weeks
mean calendar months and weeks?
I'm trying to build a schedule based on quarters not work
days.
thanks