L
Lukas Bradley
While our project members are working 8 hour days, I only want to assume I'm
going to get 6 actual work hours per day. However, I must be doing something
wrong in Project 2007.
Under Tools | Options, I change the Calendar options to have a default start
time of 10am, and default end time of 4pm. I change the hours per day to 6,
and hours per week to 30. I click the "Set as Default" button and click Ok.
I start a new project, and enter a new task with a duration of 16 hours.
Using a 6 hour workday, this should take 2.5 days. Unfortunately, Project
shows the task taking exactly 2 days, as the previous default of 8 hours per
day seems to be used. To confirm, I increase the time to 24 hours. This
should take 4 days, but does not; it takes 3 days.
How do I *really* set the default work day length to 6 hours?
Thanks for any and all help.
going to get 6 actual work hours per day. However, I must be doing something
wrong in Project 2007.
Under Tools | Options, I change the Calendar options to have a default start
time of 10am, and default end time of 4pm. I change the hours per day to 6,
and hours per week to 30. I click the "Set as Default" button and click Ok.
I start a new project, and enter a new task with a duration of 16 hours.
Using a 6 hour workday, this should take 2.5 days. Unfortunately, Project
shows the task taking exactly 2 days, as the previous default of 8 hours per
day seems to be used. To confirm, I increase the time to 24 hours. This
should take 4 days, but does not; it takes 3 days.
How do I *really* set the default work day length to 6 hours?
Thanks for any and all help.