C
Cindy
I set up a project that would utilize 2 calendars for the tasks. (an 8 hour standard calendar or a 16-hour calendar) I set up a new 16 hour a day calendar (which should equal 1 day) in Microsoft Project 2003. When I applied it to each task in the project that had a 16 hour a day schedule, the project didn't recognize it as a 16 hour calendar day. It still recognized it as an 8 hour calendar day. (Ex. This is what the project indicated: 16 hour task - Start date 4/19/04 - Finish date 4/20/04). The project should have looked like this if it was correct (Ex. 16 hour task - Start date 4/19/04 - Finish date 4/19/04). I scheduled the 16 hour day to start at 6 a.m. and finish at 10 p.m. so a 16 hour day task should start and finish on the same date. I then tried this. I went into tools, options, and changed the times there to 6 a.m to 10 p.m, hours per day 16, hours per week 80. Then applied the calendar to the task. It still didn't work. How can I get the project to recognize a 16 hour a day task? I didn't assign resources to this project and was just using it as a timeline. I would like to possibly utilize the resource information available, but need to know the ins and outs of how I can make this calendar work