J
JAckie
We set up a new calendar in MP 2000 that uses a 6.5 hour
work day. All the resources assigned to the project also
use the 6.5 hour calendar. When you click Tools/Options
and choose the calendar tab it also shows a working day of
6.5 hours. Now to the questions. Under Project/Project
Information, what should the calendar be set to? Should
that also reflect the 6.5 hour calendar or the Standard
calendar of and 8 hour workday? One of the project
managers thought this should stay with the Standard
calendar. Will the calculation on the calendar be thrown
off if one or the other calendars are used?
work day. All the resources assigned to the project also
use the 6.5 hour calendar. When you click Tools/Options
and choose the calendar tab it also shows a working day of
6.5 hours. Now to the questions. Under Project/Project
Information, what should the calendar be set to? Should
that also reflect the 6.5 hour calendar or the Standard
calendar of and 8 hour workday? One of the project
managers thought this should stay with the Standard
calendar. Will the calculation on the calendar be thrown
off if one or the other calendars are used?