Calendar-Timesheet

R

Rob Stewart

Hi there. Couple of questions:

1. I've got a request to make the work week Friday - Thursday.

Seems simple enough,, modify the standard calendar in the Ent Global to
reflect a Start on FRIDAY setting.

However, since this company is reporting total hours completed on a Weekly
basis, they want their timesheets to reflect this weekly setting (i.e seeing
the week in their timesheet be displayed from Friday to Thursday, instead of
Sunday-Saturday.)

Has anyone had success in acheiving this result? And if so,, how might it be
done?

Thanks,
-RS
 
E

eswb10

Rob -

I just did this in my Test instance to try it out before I answered.
In PWA, go to Admin > Customize Project Web Access >

At
 
E

eswb10

Rob -

Sorry about the partial post:

I tested this before I posted:

In Project Web Access, go to Admin > Customize Project Web Access

At the top of the page, select your tracking settings, then under Time
Period Settings, change the start of week to Friday.

Save your changes and you should be good.

Mark
 
G

Gary L. Chefetz \(MVP\)

Rob:

Open Project Pro choosing to Logon using an administrator account
Open The Enterprise Global
Select Tools > Change Working Time
In the calendar dialog, examine the information entered
Click the Options button
Do these two screens agree with one another?
If not, correct the settings.

--

Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com

For Project Server FAQs visit
http://www.projectserverexperts.com

For Project FAQs visit
http://www.mvps.org/project

-
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top