H
Hardip
Hi All
I've created a new calendar (by copying the standard) to allow for weekend
working. I've assigned this to the Project Information. This allows weekend
working to be included in the hammack durations. This was my original issue
as weekend working wasn't being calculated.
The project also has resources that use the standard calendar as they don't
work weekends. I've left the standard calendar assigned to these resources
in the resource sheet. However, when I assign a duration to these tasks they
also get assigned to weekends.
What is the best method to setup my project file to allow for weekend and
non-weekend working whilst ensuring all durations are being calculated? Is
there any pointers you can provide?
Thanks to Jan and Dave for responding to early posts.
Cheers, H
I've created a new calendar (by copying the standard) to allow for weekend
working. I've assigned this to the Project Information. This allows weekend
working to be included in the hammack durations. This was my original issue
as weekend working wasn't being calculated.
The project also has resources that use the standard calendar as they don't
work weekends. I've left the standard calendar assigned to these resources
in the resource sheet. However, when I assign a duration to these tasks they
also get assigned to weekends.
What is the best method to setup my project file to allow for weekend and
non-weekend working whilst ensuring all durations are being calculated? Is
there any pointers you can provide?
Thanks to Jan and Dave for responding to early posts.
Cheers, H