D
Darrell
All,
I have a PS2007 implementation that was originally set up on a 40hr work
week, and to allow for actual productivity the Project Managers allocate all
resources at 80% to determine the duration. When they did not use the server
for anything but forward scheduling this worked. However, they want to begin
using the server data for things like Resource Management, etc. and the
current configuration creates problems.
I was wondering what the impact will be if I created a second calendar to be
used for all new projects going forward with a 32hr (6.4hr day) work week and
allocate resources at 100%. Will the Server handle having two different work
weeks until the existing schedules are completed and all we have are the 32hr
work weeks remaining? Or is this a situation where we must convert everything
to the new calendar all at once?
Darrell
I have a PS2007 implementation that was originally set up on a 40hr work
week, and to allow for actual productivity the Project Managers allocate all
resources at 80% to determine the duration. When they did not use the server
for anything but forward scheduling this worked. However, they want to begin
using the server data for things like Resource Management, etc. and the
current configuration creates problems.
I was wondering what the impact will be if I created a second calendar to be
used for all new projects going forward with a 32hr (6.4hr day) work week and
allocate resources at 100%. Will the Server handle having two different work
weeks until the existing schedules are completed and all we have are the 32hr
work weeks remaining? Or is this a situation where we must convert everything
to the new calendar all at once?
Darrell