Using MS Project 2007, I have created an Administrative project plan to
account for all time off.

I would like to have the admin staff print the time off calendar for easy
viewing.

Unfortunately, the task name display and not the resource name.

Is it possible to display the resource name instead ?
- MarkP
 
M

MarkP

Jan,

Soooo sorry for the late response.

This is exactly what I needed.

THANKS !

MarkP
 
J

JulieS

Hello TC,

Yes, choose Format > Bar Styles. Select the noncritical task
type. In the Fields section at the bottom enter:
Name,Resource Names. Repeat for critical tasks.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top