I have created a project of all of my projects for the year. I need to view
and print it in Calendar view for my staff - but some of the tasks (projects)
are not showing up on the calendar. Anyone know why?
 
M

Mike Glen

Hi Carol,

Welcome to this Microsoft Project newsgroup :)

That's probably because there is insufficient space to show them all. Move
your cursor to the dividing line between the weeks until you get an Up/Down
arrow - then click and drag downwards.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top