Your request is a bit ambiguous. I think this answers your request.

Click on View | Calendar
RightMouseButton on a bar and click on Bar Styles.
Near the bottom you'll see "Field(s)". In the box to the immediate right
begin typing the name of the field you want displayed. If you want multiple
fields displayed (Name, Resource Name) then separate them with a comma.

If you just want to see the task assignment calendar for a specific
resource, then make certain the Formatting menu bar is displayed, click on
the filter (it defaults to All Tasks) and select "Using resouce ...". You
will be prompted for the resource name which you can select from the drop
down.

JLB, PMP



PMPC said:
I have a master schedule with 41 linked projects. they all share the same
resources and I want to deplay the resource in calendar view can someone
help me with this, thanks
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top