Calendar view

D

dumbuser

How can a display only the task name on the bar in the calendar view. It is currently displaying duration also and I don't want that to display.
 
G

Gérard Ducouret

Hello,

In the Calendar view :
Format / Bar Styles...
For Critical as for Non Critical tasks... Text field : erase Duration

Gérard Ducouret

dumbuser said:
How can a display only the task name on the bar in the calendar view. It
is currently displaying duration also and I don't want that to display.
 
J

Jan De Messemaeker

Hi,

Calendar View
Format
Bar Styles
Select All
In Text Select Name
OK

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
dumbuser said:
How can a display only the task name on the bar in the calendar view. It
is currently displaying duration also and I don't want that to display.
 
M

Mike Glen

Hi dumbuser,

Welcome to this Microsoft Project newsgroup :)

Try Format/Bar Styles.../choose the bar you want to change and in the text
fields box delete the Duration field.

--
FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP

dumbuser said:
How can a display only the task name on the bar in the calendar view. It
is currently displaying duration also and I don't want that to display.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top