Hi guys!

I'm new here, and this is my first thread.

I'm trying to work with a generic calendar. So, I'd like to know if i
is possible to change the calendar showed at the Gantt to something lik
this:

"Month 3, Week 1, Day 3"

I've noticed that we can change to "Day n" format, but I'd like t
start the counting when the time period changes. So, instad of Month 13
I'd have Month 1 again (but for year 2).

Thanks in advance!

Felip
 
J

JulieS

Hello Felipe,

Welcome to the Microsoft Project Newsgroup. You can get close to
what you need just not with the full label. Set your timescale to
three tiers with the following definition
Top Tier
Units: Months
Count: 1
Label: 1,2,3
This will count calendar year months and re-start at 1 for the new
year

Middle Tier:
Units: Weeks
Count: 1
Label: 1,2,......52
Will count months on calendar through 52 and then restart at 1 for
the new year

Bottom Tier:
Units: Days
Count:1
Label: 1,2, .....
Will count days in each month.


I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
F

fdmlub

Hi JulieS!

Thanks for helping. It would be good if MS Project had some generi
Gantt, but I think your hint will help me a lot.

Thanks
 