Calendar

D

Douglas

I am using Project 2000. I went to Project Information and selected a
calendar for my entire project. If I doubleclick on a task, it says the
Standard Calendar. Why does it not say the Calendar I selected in Project
Information.?

Thanks

Douglas
 
J

JulieD

Hi Douglas

if you doubleclickon a task it says "standard calendar" where?

the only reference to calendars for tasks is when a "task calendar" has been
asssigned - these are not assigned automatically - if one hasn't been
assigned the task will say "none" and the task will get its working time
definition from your project calendar, if however, a task calendar has been
assigned then that will over-ride the project calendar.

So if your tasks have task calendars assigned and you don't want this, set
the task information / advanced tab - calendar option back to "none".

Cheers
JulieD
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top