W
wandatwitch
Hello,
I am still trying to learn Project and have run into an issue with
calendars. I have changed the standard calendar to have Saturday and Sundays
as working days. I did this under tools - change working times. I am
working in the Gannt Chart View which shows weekend as working but see that
the tasks I am putting in reflect the weekend as Non working -it is extending
my completion date out way past where it should be. When I view in the
calendar view it shows the weekend as non working. I have not assigned any
resources to the tasks at this point and I have tried looking at the resource
calendar but it will not let me change anything because I have not assigned
resources. Any ideas?
I am still trying to learn Project and have run into an issue with
calendars. I have changed the standard calendar to have Saturday and Sundays
as working days. I did this under tools - change working times. I am
working in the Gannt Chart View which shows weekend as working but see that
the tasks I am putting in reflect the weekend as Non working -it is extending
my completion date out way past where it should be. When I view in the
calendar view it shows the weekend as non working. I have not assigned any
resources to the tasks at this point and I have tried looking at the resource
calendar but it will not let me change anything because I have not assigned
resources. Any ideas?