Hello Allan,
It is likely that Mike is off-line currently, so pardon me for jumping
in.
You will need to either modify the standard calendar or create a new
calendar through Tools > Change working time.
Assuming you have two ten hour shifts per day for 7 days a week:
Select all column headings S through S and enter:
First Row
From: 12:00 AM To: 3:00 AM
Second Row
From 7:00 am To: 12:00 am
This give you the 4 hours per day that is nonworking time from 3:00 am
to 7:00 am
For the 24 hour calendar, I would just use the 24 hour calendar which
comes with Project. The working time in that calendar is defined as
12:00 am to 12:00 am.
I suggest however, that you will also need to create separate
calendars for your groups of resources. The *project* calendar could
be the 24 hour or 20 hour, but assuming your resources do not work 20
or 24 hours per day, you'll want to create the calendars for the 7:00
am to 5:00 pm staff and the 5:00 pm to 3:00 am staff. If you go with
the 12 hour per day, again you'll need one calendar for the 7:00 am to
7:00 pm staff and another calendar for the 7:00 pm to 7:00 am staff.
For guidance on creating calendars which span over midnight see the
"Night Shift" calendar which comes with Project.
I also suggest reading FAQ # 5 "Default Working Hours" at:
http://project.mvps.org/faqs.htm
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project